The Evidence Trail Behind a Safe Stop: Commissioning STO and SS1 After a Bosch Drive Retrofit

Bosch Motors & Controls UK
The Evidence Trail Behind a Safe Stop: Commissioning STO and SS1 After a Bosch Drive Retrofit

Photo: Nuclear Regulatory Commission from US, CC BY 2.0, via Wikimedia Commons

Retrofitting a Bosch drive onto an existing machine usually brings safety functions that were not previously present as monitored functions. Where a contactor once dropped the motor, Safe Torque Off now disables the output stage under software and hardware supervision, and Safe Stop 1 adds a controlled deceleration ahead of it. Both carry a claimed performance level. Neither is worth anything without evidence.

Start with the design basis, not the terminals

Commissioning begins before the first cable is landed. The risk assessment should already establish the required performance level under EN ISO 13849-1 or the required SIL under IEC 62061, the stop category in accordance with BS EN 60204-1, and whether SS1 is needed to meet the stopping time demanded by the hazard. If an emergency stop is involved, ISO 13850 and stop category 1 apply.

The same assessment should set out the reaction time budget \u2014 detection, processing, and the mechanical rundown of the axis \u2014 because that budget is what the functional test will later be measured against. A safety function commissioned without a stated budget cannot be validated, only demonstrated.

Wiring verification

Note also what STO does not do: it provides no holding torque. Any suspended load, vertical axis or brake-dependent arrangement must be assessed on that basis, and the brake circuit commissioned as part of the same exercise.

Parameter verification

The safety function must be enabled and configured deliberately, and the resulting set captured. Confirm the assignment of safe inputs, the SS1 deceleration ramp, the delay between the ramp completing and STO engaging, the brake control and release sequencing, and the diagnostic reporting presented to the operator.

Export the parameter file, record the firmware version, and store both with the commissioning pack. A parameter set that exists only inside the drive is not a record; it is a liability the day a board is replaced.

The functional test

Test with the motor uncoupled, or with the load secured and the hazard eliminated. For each function, and for each channel individually:

  1. Apply the demand and confirm the output stage is disabled within the measured response time.
  2. Confirm no torque is produced at the motor terminals.
  3. Confirm the diagnostic status reported by the drive matches the demand.
  4. Confirm the drive will not start while the demand is present, and that restart requires a deliberate reset.
  5. For SS1, confirm the axis follows the defined deceleration and that STO engages only after the delay, then compare the measured stopping time against the risk assessment budget.
  6. Introduce a single-channel demand to prove cross-fault detection operates as designed.

Record the instrument used, its calibration status, the measured times, the date, and the name of the person who witnessed the test.

The paperwork that survives an audit

A commissioning pack that holds up three years later typically contains:

The last item is the one most often missing. PUWER 1998 requires work equipment to be maintained in an efficient state and inspected where deterioration could give rise to risk, with records kept. A safety function whose proof test exists only in someone's memory does not satisfy that duty. Insurers and engineering inspection bodies increasingly ask for exactly this documentation after a claim, and the absence of a test record is difficult to argue around.

Mistakes that convert a function into an assumption

Closing the loop

A safety function is a claim about behaviour under fault. Commissioning is the process of turning that claim into measured fact, and the documentation is what carries the fact forward to the next auditor, the next maintenance engineer and the next insurance review. The wiring takes an afternoon; the evidence is what makes the afternoon count.

All Articles

Related Articles

Fluting, Frosting and the Voltage You Cannot Hear: A Bearing-Current Checklist for Retrofitted 400 V Drives

Fluting, Frosting and the Voltage You Cannot Hear: A Bearing-Current Checklist for Retrofitted 400 V Drives

The Ageing Motor Verdict: Rewind, Replace or Retrofit With the Numbers in View

The Ageing Motor Verdict: Rewind, Replace or Retrofit With the Numbers in View

Drive Data as an Energy Meter: A Sceptical Guide for UK Plant Teams

Drive Data as an Energy Meter: A Sceptical Guide for UK Plant Teams